Xergi is to deliver its largest biogas plant to date to Danish dairy company Arla Foods with green energy for the production of milk powder.

The Nature Energy Videbaek biogas plant is expected to be up and running in the autumn of 2018, using converting biomass to electricity and heat.

The main shareholder is the energy company Nature Energy while Arla Foods, Xergi and local farmers’ association Videbaek Biogas have smaller holdings in the plant.

Xergi CEO Jorgen Ballerman said: “We have been involved in the project development right from the start 5-6 years ago. Therefore, we are very pleased that we are now on target with the project.”

With five biogas digesters each with a capacity of 9,500 cubic metres the biogas plant can handle about 600,000 tonnes of biomass a year and produce 16.5 million cubic metres of bio-methane.

The plant is thus the largest Xergi has ever built since the company began constructing biogas plants more than 30 years ago.

Jorgen said: “The plant will be built in accordance with our design principles which over the years have ensured stable and high gas production at a number of large biogas plants delivered in countries such as UK, France, USA and Denmark.

“The plant will be equipped with a number of new technical solutions developed by Xergi. The solutions improve the gas yield from organic residues from the food industry, agriculture and households. The Nature Energy Videbaek plant will therefore – internationally – become an important reference plant in the transition to green energy.”

The biogas plant provides Arla Foods with the opportunity of using green energy, which is partly produced by one of the company’s own by-products. Every year a total of 40,000 tonnes of the residual product Perlac 14 will be digested in the biogas plant.

The rest of the 600,000 tonnes of biomass will primarily come from agriculture in the form of manure and deep litter, but a smaller quantity of residual products from other food industries also ends up in the biogas plant. The residual biomass is used as fertiliser by local farmers.

Jorgen said: “When manure and deep litter are treated in the biogas plant the nutrients are made easily available for the crops. This means that farmers can utilise the fertilisation value of their manure better and at the same time new nutrients recycled from industry are continuously being supplied to agriculture. In this way agriculture receives greener and more environmentally-friendly fertiliser while Arla Foods receives a green energy supply.”

The plant is being constructed in the village of Trøstrup south of Videbaek in the western part of Denmark and will handle produce 16.5 million cubic metres of bio-methane and handle 600,000 tonnes of biomass annually.

It has three primary biogas digesters with a capacity of 9,500 m3 each and two secondary digesters with a capacity of 9,500 m3 each.